 6.  Align the two indentations in the inverter enclosure with the two triangular mounting tabs of the 
bracket, and lower the inverter until it rests on the bracket evenly.
 7.  For inverters with DC Safety Unit -   s ecure the DC Safety Unit bracket to the wall:
 8.  Secure the StorEdge Connection Unit bracket to the wall:
Mark the location of the bracket screw for the StorEdge Connection Unit and drill the hole.
 
Fasten the bracket using a standard bolt.
 
Verify that the bracket is firmly attached to the mounting surface.
 
 9.  Insert the two supplied screws through the outer heat sink fin on both sides of the inverter and into 
the bracket (see Figure 10). Tighten the screws with a torque of 4.0 N*m / 2.9 lb.*ft.
 10.  Remove the inverter cover: Open the inverter cover's six Allen screws and carefully pull the cover 
horizontally before lowering it.
StorEdge Inverter Installation Guide MAN-01-00390-1.1
Figure 10: Hanging the inverter on the bracket
Figure 11: StorEdge Connection Unit bracket