Chapter 8: Commissioning the Installation

This chapter describes how to activate the system, pair the power optimizers to the inverter and verify 
the proper functioning of the system.

Step 1: Activating the System

 1.  Verify that the inverter ON/OFF switch is OFF.
 2.  Move the StorEdge Connection Unit ON/OFF switch to the ON position. 
WARNING!
ELECTRICAL SHOCK HAZARD. Do not touch uninsulated wires when the inverter cover is
removed.
RISQUE D'ÉLECTROCUTION, ne touchez pas les fils non isolés lorsque le couvercle de
l'onduleur est retiré.