Chapter 5: Commissioning the Installation

Chapter 5: Commissioning the Installation
This chapter describes how to activate the system, pair the poweroptimizers to the inverter and verify 
the proper functioning of the system.

Removing the Inverter Cover

If the inverter cover is not already removed, use the following procedure for cover removal.
To remove the inverter cover
 1.  Turn the inverter ON/OFF switch to OFF. Wait 5 minutes for the capacitors to discharge.
WARNING!
If the inverter was operating properly (power was produced by the power optimizers), the following
 
message is displayed.
This message is displayed until the DC voltage is safe (50V). Do not open the cover until the voltage is
safe or until at least five minutes have passed.
 2.  Turn the Connection Unit (if applicable) to OFF.
 3.  Disconnect the AC to the inverter by turning OFF the circuit breakers on the distribution panel. 
 4.  Open the inverter cover's six Allen screws and carefully pull the cover horizontally before lowering it.
42
D C
V O L T A G E
N O T
D O
N O T
D I S C O N N E C T
V D C :
7 2 . 0
StorEdge Inverter Installation Guide MAN-01-00390-1.1
S A F E