Installation Guidelines
Installation Guidelines
Frame-mounted power optimizers are mounted directly on the module frame ,
regardless of racking system (rail-less or with rails). For installation of frame-mounted
power optimizers, refer to http://www.solaredge.com/sites/default/files/installing_
frame_mounted_power_optimizers.pdf.
The steps in this chapter refer to module add-on power optimizers. For smart
modules, start from . Also refer to the documentation supplied with the smart
modules.
The power optimizer can be placed in any orientation.
If connecting more modules than optimizer inputs in parallel, use a branch cable. Some commercial
power optimizer models h ave a dual input.
Position the power optimizer close enough to its module so that their cables can be connected.
Make sure to use power optimizers that have the required output conductor length:
Minimize the use of extensions between power optimizers.
o
You can use extension cables between rows and from the end of string to the inverter.
o
Do not use extension cables between the modules and the power optimizers, or between two
o
power optimizers within a string.
The minimum and maximum string length guidelines are stated in the power optimizer datasheets.
Refer to the D esigner for string length verification. The D esigner is available on the SolarEdge website
at http://www.solaredge.com/products/installer-tools/site-designer#/.
Completely shaded modules may cause their power optimizers to temporarily shut down. This will
not affect the performance of the other power optimizers in the string, as long as the minimum
number of unshaded power optimizers connected in a string of modules is met. If under typical
conditions fewer than the minimum optimizers are connected to unshaded modules, add more
optimizers to the string.
T o allow for heat dissipation, maintain a 2.5 cm / 1" clearance distance between the power optimizer
and other surfaces, on all sides except the mounting bracket side.
NOTE
The images contained herein are for illustrative purposes only and may vary depending on product
models.
14
Figure 2: Power optimizer clearance
StorEdge Inverter Installation Guide MAN-01-00390-1.1