Connecting Communication to the Meter

Connecting Communication to the Meter
If a meter was installed, connect it to the StorEdge Connection Unit as described in the following table. 
For detailed information refer to the installation guide supplied with the meter.
Recommended cable type
(min-max mm
2
RS485 0.2 mm
(0.2 - 1.5 mm
shielded twisted pair, 600V
insulated
Insert the cable from the meter through the communication gland (labeled 1).
Connect as illustrated below:
38
StorEdge Connection
2
)
Unit
2
),
Ext. Devices 7-pin terminal
block: B, A, G
Figure 26: Connection to a meter
StorEdge Inverter Installation Guide MAN-01-00390-1.1
Meter connection
RS485 4-pin terminal block: B, A, G