Figure 29: Connection to grid and backed-up loads (StorEdge Connection Unit with glands)
To connect the AC cables - StorEdge Connection Unit with conduits:
NOTE
For Australia: Use 10mm
1. Insert the cable through the appropriate conduit opening:
For grid connection ( from the main distribution panel) and for grounding: insert through the
bottom opening labeled AC1 GRID
For backed-up loads connection ( from a backed-up loads panel): insert through the side opening
labeled BACKUP
2. Connect the grounding cable to the terminal block lableled
3. Connect the AC wires according to the labels on the terminal blocks: Use a standard flat-blade
screwdriver to connect the wires to the spring-clamp terminals:
a. Insert the screwdriver into the square opening at the top of the terminal block a nd press to open
clamp mechanism.
b. Insert the wire into the round opening and release t he screwdriver to spring back and clamp the
wire.
Figure 30: Connection to grid and backed-up loads (StorEdge Connection Unit with conduits)
StorEdge Inverter Installation Guide MAN-01-00390-1.1
2
wire to connect the inverter to ground.
Chapter 4: StorEdge Inverter Connections
.
41