4
Project planning
4.1
Manufacturer of the machine
4.2
Operator of the machine
4.3
Design
8014253/YST2/2016-04-11 | SICK
Subject to change without notice
This chapter includes important information about the proper integration of the safety
light curtain in machines for planners, developers and designers.
DANGER
Hazard due to lack of effectiveness of the protective device
Persons and parts of the body to be protected may not be recognized in case of non-
observance.
Use of the safety light curtain requires a risk assessment. Check whether addi‐
b
tional protective measures are required.
Comply with the applicable national regulations derived from the application (e.g.,
b
work safety regulations, safety rules, or other relevant safety guidelines).
Do not combine the components of the safety light curtain with components from
b
other safety light curtains.
Apart from for the procedures described in this document, the components of the
b
safety light curtain must not be opened.
The components of the safety light curtain must not be tampered with or changed.
b
Improper repair of the protective device can lead to a loss of the protective func‐
b
tion. Do not carry out any repairs on the device components.
DANGER
Hazard due to lack of effectiveness of the protective device
Persons and parts of the body to be protected may not be recognized in case of non-
observance.
Changes to the electrical integration of the safety light curtain in the machine con‐
b
trol and changes to the mechanical installation of the safety light curtain require
another risk assessment. The results of this risk assessment may require the oper‐
ator of the machine to meet the obligations of a manufacturer.
Apart from the procedures described in this document, the components of the
b
safety light curtain must not be opened.
The components of the safety light curtain must not be tampered with or changed.
b
Improper repair of the protective device can lead to a loss of the protective func‐
b
tion. Do not carry out any repairs on the device components.
This chapter contains important information about the design.
Information about the individual steps for installation of the device:
page
27.
PROJECT PLANNING
see "Mounting",
O P E R A T I N G I N S T R U C T I O N S | deTec4 Core
4
17
Need help?
Do you have a question about the deTec4 Core and is the answer not in the manual?