Section 6
Testing IED operation
6.7

Testing the protection functionality

Each protection function must be tested individually by secondary injection.
Verify operating levels (trip) and timers.
Verify alarm and blocking signals.
Use the disturbance handling tool in PCM600 to evaluate that the protection function has
received the correct data and responded correctly (signaling and timing).
Use the event viewer tool in PCM600 to check that only expected events have occurred.