Verifying Analog Primary And Secondary Measurement; Testing The Protection Functionality; Forcing Of Binary I/O Signals For Testing; Forcing Concept - ABB RELION 670 Series Commissioning Manual

Hide thumbs Also See for RELION 670 Series:
Table of Contents

Advertisement

Section 9
Testing IED operation
Procedure
1.
Click the Function test modes menu.
The Function test modes menu is located in the local HMI under Main menu/Test/
Function test modes.
2.
Browse to the function instance that needs to be released.
3.
Set parameter
9.6

Verifying analog primary and secondary measurement

Verify that the connections are correct and that measuring and scaling is done correctly. This
is done by injecting current and voltage to the IED.
1.
Inject a symmetrical three-phase voltage and current at rated value.
2.
Compare the injected value with the measured values.
The voltage and current phasor menu in the local HMI is located under Main menu/
Measurements/Analog primary values and Main menu/Measurements/Analog
secondary values.
3.
Compare the frequency reading with the set frequency and the direction of the power.
The frequency and active power are located under Main menu/Measurements/
Monitoring/ServiceValues(MMXN)/CVMMXN:x. Then navigate to the bottom of the list
to find the frequency.
4.
Inject an unsymmetrical three-phase voltage and current, to verify that phases are
correctly connected.
If some setting deviates, check the analog input settings under
Main menu/Configuration/Analog modules
9.7

Testing the protection functionality

Each protection function must be tested individually by secondary injection.
Verify operating levels (trip) and timers.
Verify alarm and blocking signals.
Use the disturbance handling tool in PCM600 to evaluate that the protection function has
received the correct data and responded correctly (signaling and timing).
Use the event viewer tool in PCM600 to check that only expected events have occurred.
9.8

Forcing of binary I/O signals for testing

9.8.1

Forcing concept

Forcing of binary inputs and outputs is a convenient way to test wiring in substations as well
as testing configuration logic in the IEDs. Basically it means that all binary inputs and outputs
on the IED I/O modules (BOM, BIM, IOM & SOM) can be set to a value (i.e active or not-active),
selected by the user, while the IED is in test mode. For inputs, this is true regardless of the
62
Blocked for the selected function to No .
Apply input signals as needed according to the actual hardware and the
application configuration.
1MRK 505 339-UEN B
M11745-2 v13
GUID-125B6F28-D3E5-4535-9CD6-6C056B79F496 v2
GUID-3FD8C676-10E5-432A-8CD5-4643299AD794 v1
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Reb670

Table of Contents