8. Adjustment of gap between the magneto rotor and ignition coil ass'y

(1) Loosen the two Bolts M4 x 18 [27] so as to
temporarily retain the Ignition Coil Ass'y [23].
(2) Insert a 0.3-mm thickness gauge into the
clearance between the Ignition Coil Ass'y [23]
and the periphery of the magnetic steel portion
of the Magneto Rotor [14].
(3) In this state, firmly tighten the two Bolts M4 x 18
[27].

9. Electric wiring

Perform wiring according to the following figure.
(1) Connect the connector of the Cord [21] to the Ignition Coil Ass'y [23].
(2) Connect the Earth Cord [11] to Crank Case (A) [6] using the Bolt M4 x 10 [12].
(3) Fit the Stop Switch [196] to the Rear Handle Set [114] with the "1" mark on the left side.
(4) Connect the connectors of the Cord [21] and Earth Cord [11] to the connectors of the Stop Switch [196].
(5) Place the Switch Cover [197] on the Stop Switch [196].
NOTE: Do not get the Cord [21] and the high-voltage cord pinched by other parts.
• Electric wiring
[6]
[146]
[11]
[142]
[21]
• Adjustment of gap between the magneto rotor and ignition coil
ass'y
[23]
0.2 to 0.4 mm
[14]
[12]
High-voltage cord
-17-
0.2 to 0.4 mm
[196]
[114]
[22]
[27]
[23]
[27]
[197]