4.6 Making a TEOAE recording
4.6.1 Probe Check
Click on the Probe Check button to run the probe check before testing. Click again to stop the probe check.
4.6.2 Start, Stop & Pause
Press Start to start testing.
Press Stop to stop testing.
Press Pause to pause during testing.
4.6.3 Probe Check Graph
The Probe Check Graph displays the ongoing probe status during testing. Change the display gain using the
up and down arrows above the graph.
The Probe Check Graph will also give an indication of probe status (e.g., leaking, blocked) during testing as
the red or blue curve will move away from the original probe check setting (grey curve).
4.6.4 Stimulus Graph
The Stimulus Graph displays the click stimulus being presented to the ear as a function of pressure (Pa)
over time (ms). Change the display gain using the up and down arrows above the graph.