Installation And Removal Of Modules; Preparations; Connect And Put On Grounding Strap - Siemens SICAM RTU User Manual

Table of Contents

Advertisement

Installation
1.3

Installation and Removal of Modules

Warning
The activities described in this section presume that the grounding connection between SICAM AK 3 and
cabinet or rack has been properly carried out and that these are earthed.
1.3.1

Preparations

1.3.1.1

Connect and put on Grounding Strap

The grounding strap can be connected directly to the board rack. The connection point is lo-
cated on the left side panel of the board rack •.
SICAM AK
1
36
ACHTUNG
HANDHABUNGS-
VORSCHRIFTEN
BEACHTEN
ELEKTROSTATISCH
GEFÄHRDETE
BAUELEMENTE
CM-2844
PS -263x
CP -2016
DI-2110
DI-2110
CP-2019
DO- 2210
A I-2301
A I-2300
P S-263x
SICAM AK
Designation
Grounding Strap
CM-2846
PS -263x
CP-2016
DI-2110
DI-2110
DI- 2110
DI-2110
CP-2019
DO-2210
SICAM AK
1
SICAM RTUs, SICAM AK 3 User Manual
Edition 07.2016, DC2-028-2.03
A I-2301
AI-2300
A I-2300
CP-2019
DI-2110
DI-2110
DI-2110
DO- 2210
A I-2301
P S-263x
SICAM AK
Item-Number/MLFB
TF3-133
6MF13140DB330AA0