4. CASTER INSTALLATION
1. Lay each module on it's side so that the display/Name panel is on the right side as you face the front
of the module. Position the module so you're facing the bottom of the unit. (Figure 3)
2. Locate the three caster mounting holes on the left side, and four mounting holes on the right side of
the module. (Figure 3)
3. Secure one caster assembly to the rear base of the module using three (3) 10-32 x 1/2 Philips
Screws. (Figure 4)
4. Secure the remaining caster assembly to the front base of the module using four (4) 10-32 x 1/2 Phil-
ips Screws. (Figure 4)
5. Repeat steps 7-10 for each module in the system.
3 Caster Assy
mounting
screw holes
FIGURE 3: POSITION MODULE FOR CASTER INSTALLATION
Screw Caster Assy to
Rear of T1000 Module
6. Set the module(s) upright on the casters.
7. Position the module(s) near their final installation location.
NOTE: The casters roll in a straight line, but do not swivel. To turn the module, slide the front
or back end laterally to change direction.
8. Facing the front of the modules, arrange the modules left to right in the following order:
Transformer Module (if available)
Power Module
Battery Module with output panel(if available)
Second Battery Module without output panel (if available)
T1000 Series UPS Installation and Operation Manual – 91074-002
FIGURE 4: ATTACH CASTER ASSEMBLIES
4 Caster Assy
mounting
screw holes
Screw Caster Assy to
Front of T1000 Module
E-3

Advertisement

Table of Contents
loading

Table of Contents