install the remaining mounting kits as described in steps 1-5 (Fig-
ure 3).
FIGURE. 2: INSTALL REMAINING 2-POST
4. Install the Module in the 2-Post Rack
CAUTION: Battery Modules weight 150 lb. (68 kg).
Use lifting aids and proper lifting techniques.
NOTE: The T1000 System modules must be arranged top-to-bottom in the following relative order:
Transformer Module (if present)
Power (UPS) Module
Battery Module w/Output Panel (if present)
Battery Panel w/o Output Panel (if present)
1. Follow the vertical arrangement of T1000 modules as indicated in the NOTE above. Secure the lowest
module in the 2-Post rack to the bottom four brackets. (Figure 4)
• Each Front Bracket: 2 x Phillips 10-32 x 1/2" in the center slots. (Figure 3)
• Each Rear bracket: 1 x Phillips 10-32 x 1/2" in the center slots. and 2 x Phillips 8-32 x 1/4" screw
each in the top and bottom slot, (Figure 4)
2. Repeat Step 7 for the remaining modules, working from bottom to top. (Figure 6)
3. Go to T1000 Installation and Operation Manual, 91074, for cabling instructions.
FIGURE. 4: MOUNT MODULE ON 2-POST FIXED BRACKETS
E-6
FIXED BRACKETS
Phillips 10-32 x
1/2" screws
T1000 Series UPS Installation and Operation Manual – 91074-002
FIGURE. 3: INSTALL REMAINING
MODULE BRACKETS
Phillips 8-32 x
1/4" screws