Unpack the 80kVA Model UPS

The 4400 80kVA UPS has C_channel skids for a base. The skids are bolted to the shipping pallet to se-
cure the UPS during shipping. Folow the directions below to unship the 80kVA UPS.
TOP HEAVY EQUIPMENT. THIS EQUIPMENT WILL TIP OVER EASILY
UNTIL FIXED IN PLACE.
Lift and move carefully, and only with adequate equipment and trained
personnel. IMPROPER LIFTING CAN RESULT IN INJURY OR DEATH.
Carefully inspect the UPS for shipping damage. Units shipped within North America and NAFTA are
shrink wrapped.
1
5. Use a forklift or pallet jack to transport the UPS to
it's installation location. See Section 8.3.
10
CAUTION
1. Remove shrink wrap.
2. Unbolt the UPS base from the
shipping pallet.
3. Use a forklift to lift the UPS off
the shipping pallet.
4. Put down the UPS and remove
the pallet.
FIGURE 4.3 – UNSHIPPING 80KVA UPS