Rotax 912 Series Maintenance Manual page 57

Hide thumbs Also See for 912 Series:
Table of Contents

Advertisement

4) Maintenance schedule procedures (maintenance check list)
Inspections
All stated checks are visual inspections for damage and wear, unless oth-
erwise stated.
Specified period
All listed work must be carried out within the specified period.
Maintenance
Checks are carried out as per the maintenance check lists, where type
check lists
and volume of maintenance work is outlined in key words. See chapter
05-20-00 section 5.1).
- The lists must be photocopied and filled out for each maintenance
Extra inspections
- The respective check (e.g. 100 hr. check) must be noted on the top of
- All the maintenance work carried out must be initialled in the "signa-
Maintenance re-
After maintenance, the completed check lists must be entered in the
cords
maintenance records. The maintenance must be confirmed in the log
book.
Discrepancies/re-
All discrepancies and remedial action must be recorded in a report of
medial action
findings to be generated and maintained by the company authorized to
carry out maintenance work. It is the responsibility of the aircraft operator
to store and keep the records.
Replacement of
Replacement of equipment (e.g. fuel pump, governor....) and execution of
equipment
SB (LTA) must be entered in the engine log book, stating
S/N, TSN and date.
Effectivity: 912 Series
Edition 3 / Rev. 0
BRP-Powertrain
MAINTENANCE MANUAL
check.
each page of the maintenance check list.
ture" area by the aircraft mechanic performing the task.
05-20-00
page 9
September 01/2012

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents