Siemens SICAM Manual page 42

Earth fault indicator
Hide thumbs Also See for SICAM:
Table of Contents

Advertisement

Installation and Commissioning
3.8 Signal Lamp Dimensions and Procedures
[dw̲efipcbaview̲signallamp, 1, en̲US]
Figure 3-18
NOTE
i
i
Siemens signal lamp mounting kit is provided with 4 screws. However, only 2 screws are required for
performing the mounting operation.
Battery Activation during Commissioning
Pull out the battery isolation tab as shown in Figure 3-18. Ensure that the battery is inserted as per the
correct polarity.
On removing the tab, the signal lamp gives 5 blinks (red LED) to indicate that the battery is healthy and
activated.
42
Position of Terminal in Signal Lamp for Connection to SICAM EFI
SICAM, Earth Fault Indicator, Manual
E50417-H8940-C600-A3, Edition 12.2022