PV-9661 / PV-9662
4.1.2.2.
Service Position with Extension
Cable Kit
4.1.2.2.1.
Service Position
In Service Position (1), mechanism check from the Bottom Side
of Mechanism Chassis and Capstan Stator Unit (Capstan
Motor Drive, Loading Motor Drive Circuit) check with power on
condition can be performed.
4.1.2.2.2.
Extension Cable Kit (VUZS0002)
Note:
3 types of Extension Cable -2 are included in this kit. Since
there is a difference in the number of P3501 Head Amp
C.B.A. pins between 2 Head, 4 Head, and Hi-Fi models, be
sure to use the proper cable.
Fig. 2-4
Fig. 2-5
4.1.2.2.3.
How to place the unit in the
Service Position (1)
1. Remove Top Cover, Front Panel Ass'y, Mechanism
Chassis, and Cassette Up Ass'y.
2. Connect the Extension Cables as follows:
12
Fig. 2-6