Installing and putting a TIM into operation
5.6 Configuring a TIM and setting parameters
Figure 5-48
The SDBs are transferred to a TIM as follows:
● Over the MPI interface of the TIM 4 if this is installed as a stand-alone device.
● With a TIM 3 without MPI interface and with a TIM 4 installed as a CP in an S7-300, use
● With the TIM 3V-IE, TIM 3V-IE Advanced and TIM 4R-IE via the MPI interface of the CPU
The SDBs may only be transferred after the TIM has completed its startup. The TIM's LEDs
indicate when startup is completed. For more detailed information, refer to the section
Startup activities of the TIM
Note
With the TIM 3V-IE variants and the TIM 4R-IE, the SDBs can be stored on the TIM or the
S7-300 CPU. This is specified in the parameter assignment of the module. If you decide to
store the SDBs on the TIM, the SDBs must be transferred to the module as described
above. If the SDBs are stored on the CPU, it is not necessary to transfer the SDBs
separately. The TIM receives the SDBs from the CPU during the common startup of the
modules in the S7-300 rack.
220
System data blocks (SDBs) in the program directory of the TIM
the MPI interface of the CPU via which the TIM is accessible on the S7-300 backplane
bus and can be reached to load the SDBs.
or via the Ethernet interface.
.
SINAUT ST7 Station control system - System Manual
System Manual, 05/2007, C79000-G8976-C178-06

Advertisement

Table of Contents
loading

Table of Contents