SAGEM-LINK F
Installation and Operation Manual
2.1 - Overview
This chapter explains how to verify Sagem Link F correct operation after installation. Testing
procedures are given in order to check radio system is operating according to the specifications.
The tests performed are :
•
Frequency Scan
•
Receive Signal Level
•
Tributary Tests
•
Engineering Order Wire (optional)
•
Alarm Relays and I/O Dry Loops Test (optional)
•
1+1 Verification (optional)
•
BER measurement
Required test equipment
•
Laptop Computer with a serial interface
•
Sagem Link F Pilot software
•
2 Mbit/s Bit Error Rate Analyzer
•
Digital voltmeter
Sagem Link F Field Commissioning Form
A field commissioning form is provided in order to record all measurement data and remarks during
commissioning operation.
Note
The Bit Error Rate tests are made only with the 2 Mbit/s signals. For IDU using Ethernet option, it will
be necessary to choose a configuration with at least one 2 Mbit/s tributary available. Refer to Chapter
6 for more details.
2.2 - Preliminary Verifications
Before beginning commissioning tests, it is necessary to check the following :
•
Verify all equipment for damage occurred during installation
•
Verify that all equipments are properly mounted
•
Verify antenna polarization
•
Check ODU, cable and IDU groundings
•
Measure DC Input Voltage on each terminal and record it on the commissioning form
•
Connect laptop computer to the PC DB9 connector on the IDU front panel, and run the Sagem
Link F Pilot software. Be sure to be logged in super user mode (Default password = 2345). On
the main screen verify and change if necessary :
-
Local and Remote terminal transmit frequency
-
Modulation type and Capacity
-
Local and Remote terminal nominal transmit power, ATPC should be in "OFF" position
Tributary Impedance
-