NetNumen™ U31 R06 Hardware Installation Guide
Figure 7-6 Removing a Front blank panel
1. Extractor
6. Store the blank panels in the warehouse or other moisture-proof and dust-proof places.
– End of Steps –
7.2.2 Installing a Board
This procedure describes how to install a board in an E4140 shelf by using the front board
as an example.
Note:
The procedure for installing a rear board is the same as that for installing a front board.
For an E4140 shelf, rear boards must be installed before front boards are installed.
Prerequisite
l
An
ESD
l
The position where the board is installed in the shelf is known.
SJ-20141121113158-006|2014-12-20 (R1.0)
wrist strap (or anti-static gloves) and a cross head screwdriver are ready.
2. Captive screw
7-6
ZTE Proprietary and Confidential
3. Latch