Install a single cabinet
Install multiple cabinets
14. Mount adjustable bases side by side. Measure the level of the adjustable bases by
using the spirit level, see

Figure 5-16 Adjusting the Level of Multiple Adjustable Bases

1. Spacer shim
15. Use the multimeter to measure the resistance between the adjustable base and the
concrete floor, see
The resistance value must be greater than 5 MΩ.