2.4.12 Wood gasification boiler: side panels installation

– Halfway insert 2 screws on the bottom of each side of the base – Fig. 41. Release the side panels and hook
them into the inserted screws at the bottom (Fig. 42, 43). Loosely screw the top with one self-tapping screw
and one saw tooth ring for grounding - Fig. 44.
Note!
Loosely screw the cladding screws at first; do not adjust the cladding (gap size) or tighten screws
until all cladding parts have been installed.
2 each of
Fig. 41 Insert 2 screws on each side of the base
Fig. 42 Hooking side panels with screws
at the bottom
1 x
Fig. 44 Loosely tightened screws at top of cladding.
Fig. 43 Hooking in side panels