Installing Memory Modules; Required Tools; Preliminary Steps - Fujitsu Primergy CX270 S2 Upgrade And Maintenance Manual

Server node
Hide thumbs Also See for Primergy CX270 S2:
Table of Contents

Advertisement

Main memory
7.2

Installing memory modules

Upgrade and Repair Units (URU)
Average task duration: 5 minutes
7.2.1

Required tools

Preliminary and concluding steps:
– Phillips PH2 / (+) No. 2 screw driver
Installing memory modules: tool-less
7.2.2

Preliminary steps

Perform the following steps:
"Disabling SVOM boot watchdog functionality" on page 65
Ê
Ê Locate the desired server node.
"Shutting down the server node" on page 43
Ê
Ê If applicable, remove all external cables from the server node.
"Removing the server node from the server enclosure" on page 44
Ê
"Disconnecting the BBU from the controller" on page 216
Ê
"Removing the cables" on page 45
Ê
"Removing a TESLA GPGPU card" on page 140
Ê
"Removing the air duct" on page 46
Ê
"Removing the GPGPU riser module" on page 48
Ê
"Removing the air duct brackets" on page 49
Ê
"Removing the memory slot air ducts" on page 50
Ê
Ê Identify the correct memory slot according to the mounting order described
in section
"Memory sequence" on page
228
Upgrade and Maintenance Manual
(if applicable)
224.
(if applicable)
CX270 S2

Advertisement

Table of Contents
loading