Expansion cards, interposer boards and battery backup units
6.5.7.7

Installing the air tunnel

Figure 115: Installing the GPGPU air duct
Ê Latch the bottom hook into the notch on the air duct bracket (see close-
up) (1).
Ê Secure the air duct with one screw (2).
Screw type: 6-32 x 4.7 mm
6.5.7.8

Concluding steps

Perform the following steps:
"Installing the cables" on page 57
Ê
I
For a complete cabling overview, please refer to section
overview" on page
"Installing the server node in the server enclosure" on page 62
Ê
Ê If applicable, reconnect all external cables.
"Switching on the server node" on page 63
Ê
"Enabling boot watchdog functionality" on page 74
Ê
CX270 S2
304.
Upgrade and Maintenance Manual
"Cabling
183