When joining the I/S frame with the right frame, be sure to align it with the slots in the
right frame appropriately. Then push until it meets resistance.
Pay attention to the 20.8 mm gear in the combination gear (12 mm, 20.8 mm) when
connecting the I/S frame to the right frame. It must engage the 16.8 mm gear correctly.
Leave some backlash for the combination gear (12 mm, 20.8 mm).
When attaching the I/S frame to the right frame, be sure to mount the screw on the front
first. Otherwise, the frame will bend. (See Figure 3-61.)
After installing the I/S frame onto the printer mechanism, only carry the printer
mechanism by holding the bottom frame.
Tightening torque for the screws (CBS, 3x5, F/Zn) = 8 ~ 10 kg-cm.
3-46
Figure 3-60. Order for Mounting Screws