12 | Initial start-up
After installing the unit, attach the 1600 mm [63 inch] maximum insertion
height sticker to the unit. The sticker is included with the starter kit.
Run software update
Run software update
Always carry out a software update for commissioning. This means that
your unit will start with the latest software version.
12.2 Performing a self-test
Changed CO / CO
Risk of poisoning due to excessive flue gas values.
Perform a flue gas analysis after the self-test.
n
Set the values according to the flue gas analysis specifications.
n
The self-test must be started once when the unit is first commissioned. During
the self-test, the unit is adapted to the ambient conditions.
The self-test runs automatically. The duration depends on the unit size and is
between 45 and 65 minutes. With an UltraVent extraction hood, the self-test
is extended by approx. 20 minutes.
Preparations
The unit is properly connected to water, wastewater, electricity and, for
n
gas units, to the gas supply and flue gas system as described in these in-
structions.
Check that the pan rack hooks and the air baffle are correctly fitted.
n
The left side wall is closed.
n
One GN container per blower wheel is required for the self-test.
n
90 / 100
NOTE
DANGER
values after self-test
2
80.06.083_iCombiPro-iCombiClassic_IM_en-US
Need help?
Do you have a question about the iCombi Pro and is the answer not in the manual?
Questions and answers