Remove Condensation From The Cabinet - ABB ADC-90-200-C1 Operation And Installation Manual

All-in-one 90kw dc fast charger
Table of Contents

Advertisement

Operation
Procedure
1. Measure the DC voltage between the
output terminals:
Use the voltage tester.
6.7

Remove condensation from the cabinet

Preliminary requirements
Procedure
1. Open the front and right doors. Refer to section 8.1.
2. Set the main breakers 1 and 2 to the off position:
a. Set the main breakers from the
b. Set the main breakers from the
3. Energize the EVSE. Refer to section 6.6.
4. Close the doors. Refer to section 8.2.
5. Wait four hours.
The internal heater of the cabinet heats the inside of the cabinet and lets the
condensation evaporate.
6. Open the front and right doors. Refer to section 8.1.
7. Set the main breakers 1 and 2 to the on position.
a. Set the main breakers from the
b. Set the main breakers from the
8. Close the doors. Refer to section 8.2.
62
Power module group output 1- (A)
to power module group output 1+
(B)
Power module group output 2- (C)
to power module group output 2+
(D)
EV charge cable 1 output - (E) to EV
charge cable 1 output + (F)
EV charge cable 2 output - (G) to
EV charge cable 2 output + (H)
Owner
Note: If the EVSE is off for more than two hours, condensation can occur.
E
A
Auto to the Manual position.
Manual to the Off position.
Off to the Manual position.
Manual to the Auto position.
9AKK108466A3703-EN | 001
G
F H
C
B
D