5.4.3

Install a base with reduced height

Preliminary requirements
This procedure is relevant if you want to obey the regulations for wheelchair
accessibility and the combination of the location of the installation and the
standard base does not allow for this. The solution is the base with reduced height,
installed on a curb that has a height of maximum 10 cm (4 in). For more information
and height specifications, refer to section 10.12.10.
Procedure
1. Mark the position of the holes on the
ground. For the specifications, refer to
section 10.10.4.
2. Drill and thread the holes (A).
Do not make holes in not
authorized locations, because this can
compromise the structural integrity of
the base with side entrance.
3. Guide the cables to the cable trays.
4. Align the frame (B) with the threaded
holes.
5. Install the fasteners (C) with washers.
6. Tighten the fasteners to the correct
torque. For the specification, refer to
section 10.7.
5.5

Mechanical installation

5.5.1

Mechanical installation procedure

Preliminary requirements
Procedure
1. Open the cable inlet and remove the cable gland. Refer to section 5.5.2.
2. Guide the cables through the openings in the cable guide plate. Refer to section
5.5.3.
3. Install the cabinet on the foundation.
a. For the procedure, refer to section 5.5.4.
b. For the overview of the installed EVSE, refer to section 3.4.5.
4. Install the border covers. Refer to section 8.4.
9AKK108466A3703-EN | 001
Installation engineer or
maintenance engineer
Wrenches
The cabinet is above the
foundation.
Installation
Base with reduced height.