Installing Counterbalance Valve

Refer to Figure 4-9., Rotator Counterbalance Valve.
1. Make sure the surface of the actuator is clean, free of any
contamination and foreign debris including old JLG
Threadlocker P/N 0100011.
2. Make sure the new valve has the o-rings in the counter-
bores of the valve to seal it to the actuator housing.
3. The bolts that come with the valve are grade 8 bolts.
New bolts should be installed with a new valve. JLG
3121634
4. Torque the 1/4 in. bolts 110 to 120 in. lbs. (12.4 to
5. Make sure the valve is seated against the housing valve
Figure 4-9. Rotator Counterbalance Valve
SECTION 4 - BOOM & PLATFORM
Threadlocker P/N 0100011 should be applied to the
shank of the three bolts at the time of installation.
13.5 Nm). Do not torque over 125 in. lbs. (14.1 Nm).
Torque the 5/16 in. bolts 140 in. lbs. (15.8 Nm). Do not
torque over 145 in. lbs. (16.3 Nm).
flat. If it is raised up on any side or corner, remove the
valve to determine what the obstruction is. If possible,
test this using a hydraulic hand pump or electric test.