This menu allows the master user to select which event types will
be reported using the email reporting function. By default the
first 4 options are set to report via email. Follow the procedure
below to configure the required options.
1)
Enter your Master PIN + [MENU].
2)
Enter [5] + [5] + [9] + [OK].
The keypad will display the list of current options.
Options with a preceeding tick mark are selected.
Open / Close
 Zone Alarm
 Zone Trouble
Press

OK ON OFF MENU
] and [
] keys
3)
Use the [
to program, then use the [ON] and [OFF] keys to turn on and off
the features as required.
4)
When all email options are programmed, press [OK] to save and
exit, or press [MENU] to exit without saving.

Open / Close Reports

This option allows the control panel to report 'open' and 'close'
reports via email.

Zone Alarm Reports

this option allows the control panel to report zone 'alarm' and
'restore' reports via email.

Zone Trouble Reports

This option allows the control panel to report zone 'trouble'
and 'restore' reports via email when a user turns on an area that
has faulted zones.

System Reports

This option allows the control panel to report via email
numerous system reports (e.g. AC Fail, Low Battery etc) via
email.

Access Reports

This option allows the control panel to report via email when
a valid token has been swiped eg. 'Access Granted' or 'Access
Denied' .
COMMS T EST ING
Comms > Comms Test >

Send Test Report

This menu allows you to test the reporting functions of the
Solution control panel by manually sending a Test report to
the receiving party (i.e. security company monitoring station,
mobile telephone etc).
1)
Enter [MENU] + [5] + [9] + [0]. The keypad will prompt that it is
in the process of sending a test report.
Bosch Security Systems 05/10 BLCC100I
to highlight the feature that you want
-
-
MENU 5-9-0
Solution 16
plus
Installation Manual
Comms Testing in
progress. Please wait..
Press OK or MENU
2)
If the test is successful, the keypad will prompt:
Communication Test
Successful.
Press OK or MENU
3)
If the test fails, the keypad will prompt:
Test Report Failed
Please Call for service.
Press OK or MENU
Press [OK] or [MENU] to exit.
4)
Comms > Comms Test >

Test Report Time

This menu programs the time of the day that the panel will
send the automatic Test Report to the base station receiver.
Automatic test reports are used to verify the panels ability to
report events via the telephone line on an ongoing basis.
1)
Press [MENU] + [5] + [9] + [1]. The keypad will display the
current Test Report Time.
Test Report Time
02:00am
Press  OK to SAVE
Use the left, right, up and down arrow keys to select the Test
2)
Report time required then Press [OK] to save and exit or press
[MENU] to exit without saving.
i
Scroll through the hours using the up and down arrow keys to
change the time from am to pm.
Note
Comms Programming
MENU 5-9-1
Test Time
02
:
00 am
HH
MM
9-13

Advertisement