4.1 Powering On and Starting the UPS

Prerequisites
Measure the voltage and frequency values of the UPS upstream input switches.
The line voltage range is 138–485 V AC, and the frequency range is 40–70 Hz.

4.1.1 Power-On

Context
Procedure
Step 1 If desiccant is available inside the cabinet, remove the desiccant.
Step 2 Turn on the upstream bypass and mains input switches.
Step 3 (Full configuration model) Turn on the UPS bypass input switch, mains input
switch, and output switch.
----End
Issue 17 (2023-07-10)
4
D ANGER
Before power-on, ensure that the devices have passed all check items in the
section "Verifying the Installation."
Before power-on, ensure that all the UPS switches and upstream switches are
OFF.
NO TE
After the UPS is powered on, initialization begins. The MDU displays the initialization
progress bar.
Copyright © Huawei Digital Power Technologies Co., Ltd.