Maintenance and service

9.2 Maintenance plan

Damage to property due to foreign objects inside the station
During maintenance work, foreign bodies such as dirt, tools or loose components may remain
in the charging station. This can result in a short-circuit, reduced cooling capacity or increased
running noise. The charging station may be damaged.
• During maintenance work, make sure that no foreign objects remain in and on the
charging station.
• Fasten loose parts again after maintenance work.
• Remove accumulated dirt.
9.2
Maintenance plan
The following service measures are necessary to maintain the functionality and operational
safety of the dispenser.
Times of testing
After commissioning, carry out the checks according to the local regulations but, at a
minimum, at the following intervals:
• 6 months after commissioning
• 12 months after commissioning
After the first year, perform the checks every 12 months. Perform the checks at shorter
intervals if necessitated by the ambient conditions of the SICHARGE D charging station and
dispenser (e.g. high dust exposure).
Checking the charging station
Follow the inspection steps from the document with order number 8EM5907-0AA00-7AA3
"Preventive Maintenance Checklist
(https://support.industry.siemens.com/cs/us/en/view/109814289)".