Valve Replacement

Important: Always shut off gas supply/120 volt power prior to servicing the
gas valve.
1. Turn unit off and cool to room temperature.
2. Remove outer enamel or steel panels (see instructions in the panel removal
section in this manual).
3. Remove outer safety barrier and inner glass (firebox glass)–see instruc-
tions in this manual.
4. Remove all media and logs (if installed) — set aside.
5. Remove inner base panels (see panel section in this manual).
6. Remove the trim cover on the right side of the burner by lifting it off. Also,
remove the burner surround by sliding it to the left and lifting it off.
Trim cover
Burner Surround
7. Remove eight screws in the locations shown below (four at front and four
at rear). Slide the burner to the left, away from the orifice, and lift out.
8. Remove 13 screws in locations shown below.
3RD ANGLE
TOLERANCES UNLESS
PROJECTION
OTHERWISE STATED
DIMENSIONS
0.000 = 0.01 CRITICAL
0.000 = SPECIFIED TOLERANCE
DO NOT SCALE
0.000 = 0.031
DRAWING
0.000 REF = REFERENCE ONLY
UNITS IN INCHES
ANGULAR = 1
THIS DRAWING IS THE PROPERTY OF FPI LTD., IT MAY NOT BE COPIED IN WHOLE OR IN PART, OR DISCLOSED TO A THIRD PARTY WITHOUT OUR PRIOR WRITTEN CONSENT.
102
| City Series CP60E
3RD ANGLE
TOLERANCES UNLESS
PROJECTION
OTHERWISE STATED
DIMENSIONS
0.000 = 0.01 CRITICAL
0.000 = SPECIFIED TOLERANCE
DO NOT SCALE
0.000 = 0.031
DRAWING
0.000 REF = REFERENCE ONLY
UNITS IN INCHES
ANGULAR = 1
FIREPLACE PRODUCTS
-
MAT'L :
THIS DRAWING IS THE PROPERTY OF FPI LTD., IT MAY NOT BE COPIED IN WHOLE OR IN PART, OR DISCLOSED TO A THIRD PARTY WITHOUT OUR PRIOR WRITTEN CONSENT.
INTERNATIONAL
SHEAR/ PUNCH/ FORM
PROCESS :
1:24
CP60 MAIN ASSEMBLY
SCALE:
PART :
11/25/2021
PART NO:
DWN:
DATE:
457-500
DATE:
E.C.N.:
SIGN:
9. Disconnect the spark electrode, flame sense, and stepper motor from the
IFC board (see wiring diagram for location).
10. Lift valve tray out partially and disconnect flexible gas connection on the
valve inlet side. Remove the valve tray and replace it with the new valve
tray & valve assembly gasket.
FIREPLACE PRODUCTS
-
MAT'L :
INTERNATIONAL
SHEAR/ PUNCH/ FORM
PROCESS :
1:24
CP60 MAIN ASSEMBLY
SCALE:
PART :
11/25/2021
PART NO:
DWN:
DATE:
457-500
E.C.N.:
SIGN:
DATE:
REV:
-
11. Reverse steps 10-1 to complete.