3.2.2 Base Installation Flowchart

Figure 3-6

Figure 3-6 Base Installation Flowchart

3.2.3 Positioning Base

Two steps are required for positioning the base.
1. Marking
a. Confirm the position for installing the cabinet according to the reference
dimensions and base dimensions given in the engineering design diagram.
b. Use a measuring tape to measure the position.
c. Use an ink marker to mark the position.
Figure 3-7
SJ-20110909101511-005|2011-12-31 (R1.1)
shows the base installation flowchart.
shows the drilling diagram.
3-5
ZTE Proprietary and Confidential
Chapter 3 Cabinet Installation