3.2.2 Base Installation Flowchart
Figure 3-6
Figure 3-6 Base Installation Flowchart
3.2.3 Positioning Base
Two steps are required for positioning the base.
1. Marking
a. Confirm the position for installing the cabinet according to the reference
dimensions and base dimensions given in the engineering design diagram.
b. Use a measuring tape to measure the position.
c. Use an ink marker to mark the position.
Figure 3-7
SJ-20110909101511-005|2011-12-31 (R1.1)
shows the base installation flowchart.
shows the drilling diagram.
3-5
ZTE Proprietary and Confidential
Chapter 3 Cabinet Installation