ZXA10 C300 Cabinet Installation Guide (19 Inch)
2.4 Installation Environment Check
This topic includes the following:
l
Construction Check
l
Indoor Environment Check
l
Power Supply Check
l
Grounding Cable Check
l
Security Check
l
Other Supporting Facilities Check
2.4.1 Construction Check
Implement the following construction checks:
l
Check civil work and make sure that indoor walls are dry.
l
The equipment room must be large enough for holding all cabinets.
l
The door must be greater than 3 meters in height and 1 meter in width.
l
The load bearing capacity for the equipment floor must be more than 450 kg/m
bearing capacity for the non-equipment floor must be at least 300 kg/m
l
Use air conditioners to keep the temperature and humidity within range.
l
Take dust-proof measures to protect walls and roof.
l
Lighting wires and power cables must be grounded and hidden.
l
Make sure that no drain pipe passes through the equipment room.
l
Label the location and measurement of the reserved hidden ducts. The hole size must
be 400 mm × 400 mm. Ducts and troughs must be damp-proof.
l
The anti-shock level must be up to seven.
l
Mount lightning-arrester or rod to avoid lightning strike. Ground all metal pipes at the
entrance of the equipment room.
2.4.2 Indoor Environment Check
Table 2-1
Table 2-1 Operation Environment Requirements
Parameter
Ground resistance
Ambient temperature
Ambient humidity
Cleanness
SJ-20110909101511-005|2011-12-31 (R1.1)
lists the operation environment requirements.
Description
< 1 ohm
- 5℃ to 45℃
10% – 90%
Dust concentration with a diameter greater than 5 µm is equal
to or less than 3 × 10
conductive, magnetically conductive, or erosive.
4
grains/m
3
, and the dust is not electrically