Context
Figure 27-1 Position of the I/O expansion board
Issue 04 (2023-06-30)

Replacing an I/O Expansion Board

Fault locating:
a.
Log in to the SmartLogger WebUI, CMU WebUI, FusionSolar app, or
management system to view alarm information.
b.
Refer to the alarm handling suggestions in the alarm list.
Tools: Phillips insulated torque screwdriver, insulated torque socket wrench
Power-off:
a.
Log in to the SmartLogger WebUI, CMU WebUI, FusionSolar app, or
management system and send a shutdown command to the rack
controller.
b.
Turn off the ESS output DC switch 1Q2.
c.
Turn off the ESS battery rack DC switch 1Q1.