Procedure
Step 1 Disconnect cables from the CMU and label the cables.
Step 2 Remove the faulty I/O expansion board.
Figure 27-2 Removing the I/O expansion board
Step 3 Install a new I/O expansion board.
Figure 27-3 Installing an I/O expansion board
Step 4 Reinstall the cables.
----End