10.4 Replacing an Air Conditioner

Prerequisites
Procedure
Step 1 Remove the air duct.
Figure 10-16 Removing the air duct
Step 2 Remove cables from the air conditioner.
Issue 04 (2023-06-30)
Fault locating:
a.
Log in to the SmartLogger WebUI, CMU WebUI, FusionSolar app, or
management system to view alarm information.
b.
Refer to the alarm handling suggestions in the alarm list.
Tools: flat-head or Phillips insulated torque screwdriver, multimeter
Power-off: Turn off the power switch of the air conditioner in the cabinet.
NO TE
The power loop of the ESS does not need to be powered off. You are advised to set
the ESS in standby or shutdown mode during replacement.
At least two persons are required to replace the component.