Huawei LUNA2000-97KWH-1H1 Maintenance Manual page 78

Smart string ess
Hide thumbs Also See for LUNA2000-97KWH-1H1:
Table of Contents

Advertisement

LUNA2000-(97KWH-1H1, 129KWH-2H1,
161KWH-2H1, 200KWH-2H1) Smart String ESS
Maintenance Manual
Figure 10-12 Removing the front cover of the air conditioner
Step 4 Remove all cables from the main control board.
Step 5 Remove the main control board.
Figure 10-13 Removing the main control board
Step 6 Install a new main control board.
Step 7 Reinstall the cables of the main control board.
Step 8 Install the front cover.
Step 9 Connect the air conditioner cables.
Step 10 Install the air duct for the air conditioner.
----End
Issue 04 (2023-06-30)
NO TE
As some terminal connectors on the main control board are secured with transparent
adhesive, you need to use a utility knife to remove the transparent adhesive.
Copyright © Huawei Digital Power Technologies Co., Ltd.
10 Replacing an Air Conditioner
72

Advertisement

Table of Contents
loading