Huawei LUNA2000-97KWH-1H1 Maintenance Manual page 48

Smart string ess
Hide thumbs Also See for LUNA2000-97KWH-1H1:
Table of Contents

Advertisement

LUNA2000-(97KWH-1H1, 129KWH-2H1,
161KWH-2H1, 200KWH-2H1) Smart String ESS
Maintenance Manual
Figure 5-10 Installing the short copper bar
Step 9 Remove the insulation tape from the flat cables and install the flat cables to the
management module.
Figure 5-11 Installing the flat cables
Step 10 Install the front panel. Use an M4 Phillips insulated torque screwdriver with a
torque of 0.6 N·m.
Step 11 Install copper bars and cables for the battery pack.
Note the polarities when installing batteries. Do not connect the positive and
negative poles of a battery or battery string together. Otherwise, the battery may
be short-circuited.
After installing nuts, verify the torque. Mark the nuts whose torque has been
verified using a marker.
Issue 04 (2023-06-30)
D ANGER
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 Replacing a Battery Management Module
42