7 Electrical Installation
4.
Align the closed-loop crimp terminals with the bolt holes on main circuit terminal block.
5.
Tighten the bolts to the specified torque.
6.
Install the front cover and the keypad to their initial positions.
Note:
• For knock-out holes that you do not use for control circuit wiring, install the included rubber waterproofing grommets. For knock-
out holes that you do use for control circuit wiring, install the correct conduit to keep the protection level.
• The knock-out holes for main circuit wiring do not have rubber grommets. Install the correct conduit to keep the IP55/UL Type 12
protection level.
A - Rubber grommets
50
Figure 7.26 Install the Electrical Wires
Figure 7.27 Tighten the Terminal Block Bolts