3.5

Transporting the baling press

Always use the special bearing points for unloading the machine from a lorry using a forklift.
– Place the baling press on a smooth level surface at the installation site.
– Remove the packaging and dispose of it in an environmentally responsible manner.
– Cut through the steel straps.
– Using a forklift, lift the baling press by approximately 10 cm and remove the wooden blocks.
– Open the inspection fl aps and remove all the enclosed objects from the press chamber.
3.5.1

Transporting to another installation site

If only a short distance has to be covered, the baling press can be rolled to the application
site. At the new installation site, the fl oor must be suffi ciently resistant and the space
requirement must be met as well as containing an appropriate electrical connection.
20
Caution!
Installations on the electrical system or control cabinet may only be
carried out by a qualifi ed electrician or one of our service engineers.