Figure 5-19 Starting a capacity test
The capacity test automatically stops in any of the following cases:
When the battery discharge voltage reaches the EOD voltage plus 0.01 V, the test is complete. The test
data is used as capacity test data. Save the capacity test data record with the largest discharge capacity in
a month as the capacity test data for the month. A maximum of recent 36 capacity test records can be
saved.
----End

5.6.4 Test Data Download

5.6.4.1 Download over the LCD

Procedure
Step 1 Insert a USB flash drive into the USB port on the MDU.
Step 2 On the main screen of the LCD, choose System Info. Tap
displayed.
Step 3 Choose USB Operations > Export Logs, and select a log download path.
Issue 02 (2020-01-10)
All manuals and user guides at all-guides.com
The battery discharge voltage reaches the end of discharge (EOD) voltage plus 0.01 V.
The load fluctuation exceeds 10%.
An alarm is generated.