UPS5000-H-400 kVA & 800 kVA-NTN Quick Guide (Singapore 1-NET, 100 kVA Power Modules)
01
Installing Cabinets
1. Before installation, read the user manual carefully to get familiar with product information and safety precautions.
2. Use insulated tools when installing the equipment.
3. Only engineers certified by Huawei or its agent are allowed to install, commission, and maintain the UPS. Otherwise, personal injury or equipment damage
may occur, and the resulting UPS faults are beyond the warranty scope of Huawei.
4. This document describes the installation procedure for a single UPS. For details about how to install a parallel system, contact Huawei technical support.
Page 1
UPS cabinet: < 1300 kg UPS cabinet: 2000 mm x 1600 mm x 1000 mm 3. Only engineers certified by Huawei or its agent are allowed to install, commission, and maintain the UPS. Otherwise, personal injury or equipment damage UPS5000-H-800K-NTN Inductor cabinet: <...
Page 2
UPS5000-H-400 kVA & 800 kVA-NTN Quick Guide (Singapore 1-NET, 100 kVA Power Modules) 安装流程 Installing Cabinets (800 kVA) Unpacking Securing the Cabinet Space planning M12 bolt Spring washer Flat washer cabinet Inductor Concrete floor Expansion sleeve cabinet Expansion nut cabinet Inductor cabinet Cabinet Description...
Page 3
UPS5000-H-400 kVA & 800 kVA-NTN Quick Guide (Singapore 1-NET, 100 kVA Power Modules) Installing Rectifiers and Cables Equipotential ground point Installing Rectifiers and Cables(400 kVA) Signal cable route Power cable hole outside the cabinets Signal cable hole Signal cable routing from the inductor cabinet to the UPS cabinet Single power source...
Page 4
UPS5000-H-400 kVA & 800 kVA-NTN Quick Guide (Singapore 1-NET, 100 kVA Power Modules) Installing Rectifiers and Cables (800 kVA) Signal cable hole Signal cable route Power cable hole Equipotential ground point Signal cable routing from the inductor cabinet to the UPS cabinet Single power source •...