Battery System Installation - Alpha ESS STORION-T50 Installation Manual

Energy storage system
Hide thumbs Also See for STORION-T50:
Table of Contents

Advertisement

INSTALLATION
A≥1,000mm, make sure that the front door of the cabinet can be fully opened and there
is sufficient space for ventilation. Users can conveniently insert and extract the module
and operate the breaker.
B≥1,000mm, make sure that the rear door of the cabinet can be fully opened. Ventilation
and heat dissipation should be guaranteed. Users can also have sufficient space for
product maintenance.
4.3.1.3 Cabinet Installation
After the cabinet is removed to the installation position with a forklift or a tool. The cabinet
should be adjusted and removed to the designed position. Then open the internal door of
cabinet, and fix the cabinet with M13 screws, as shown in Figure 4-3.
Figure 4-3 Diagram of the cabinet base
When the cabinet needs to be fixed on the steel channel, Φ14 holes can be made in the steel
channel. Fix the cabinet to the steel channel with screws, as shown in Figure 4-4.
Fixed screw
channel
steel
Cable
groove
Figure 4-4 Fix the
cabinet to the steel
channel
723.5 mm
678 mm
14*24 mm
Ground
Foot screr-
Figure 4-5 Fix the
cabinet to the concrete
floor
24
25
When the cabinet is fixed to the concrete floor, make holes on the floor and fix the cabinet to the
concrete floor with expansion screws, as is shown in Figure 4-5.

4.3.2. Battery System Installation

4.3.2.1 Battery Rack Installation
That depends on the customer
4.3.2.2 Battery Installation
Figure 4-6 Remove the
battery
Step 1:
Open all the battery packages.
Figure 4-7 Battery label
information
Step 2:
Check the Battery No. and cluster No.
on the battery cover.
BAT-09
BAT-08
BAT-07
BAT-06
BAT-05
BAT-04
......
BAT-03
BAT-02
BAT-01
HV900112
Figure 4-8 Installation the battery
INSTALLATION
BAT-09
BAT-08
BAT-07
BAT-06
BAT-05
BAT-04
BAT-03
BAT-02
BAT-01
HV900112