Regumaq X-45
Mounting
6. Mounting
DANGER
Danger to life due to electric current!
There is a danger to life if live components are
touched.
!
Disconnect the product from the power supply
at all poles.
!
Check that no voltage is present.
!
Secure the product against being switching
back on again.
!
Only install the product in dry indoor areas.
WARNING
Risk of injury from pressurised components!
Media escaping under pressure can cause injuries.
!
Only carry out installation work when the
system is depressurised.
For retrofi tting an existing system:
!
Drain the system or shut off the supply pipes of
the system section and depressurise the system
section.
CAUTION
Risk of injury due to the heavy weight of the
station!
The station is heavy. Falling down can cause
injuries.
!
Always wear safety shoes during installation.
6.1
Notes on mounting
The fresh water station should not be considered
in isolation, but always in interaction with other
components of the heating system.
f
Match the design of the buffer storage cylinder and
the heat generator to the performance character-
istics of the fresh water station and the specifi c
consumption behaviour in the property.
f
When designing the heat generator, also consider
the energy consumption for heating mode.
138114082-V04.04.2022
NOTICE
Damage to property due to overpressure in the
system!
The safety valve only protects the potable water
circuit within the fresh water station.
!
Equip the potable water system with an
additional (non-shut-off) safety valve in
accordance with DIN EN 806-2.
NOTICE
Damage to property due to frost or overheating!
Frost or excessive ambient temperatures may
damage components of the station.
!
Mount the station in a dry, frost-free room
in which the ambient temperature does not
exceed 35°C during operation.
f
Before mounting the station, make sure that the pipes
to the installation site have been laid, fl ushed and leak
tested.
f
Before mounting the station, make sure that power
cables and earthing cables are routed to the installation
site.
f
Always mount the station upright, never inclined or
lying down.
f
The station must always be freely accessible even after
mounting.
f
The station should be installed as close as possible to
the buffer storage cylinder. The pipe connection must
have a nominal diameter of at least DN 20.
6.2
Wall mounting of the station
6.2.1
Required tools
Have the following tools ready for wall mounting:
•
Pipe wrench
•
Spirit level
•
Drill (8 mm masonry drill bit)
•
10 mm open-end spanner / reversible ratchet with
10 mm socket
•
32 mm open-end spanner
•
38 mm open-end spanner
•
4 mm key for screws with hexagon socket
•
Marking pen
23