7
Commissioning
7.2

Initial commissioning

7- Inbetrieb_Erstinbetrieb_1_S1
Initial commissioning
7200
Initial commissioning
7.2
7-2
1. Preparing for commissioning
The safety card has been properly configured in the Configurator.
Please ensure that you only configure the safety functions that are
actually wired up to the safety card inputs.
INFORMATION
When configuring the safety card, please refer to the Configura-
tor's online help.
The safety card is installed on the servo amplifier (See "Installation"
chapter).
The device number (serial number and order number) of the safety
card on the servo amplifier matches the device number of the safety
card in the Configurator.
The servo amplifier is ready for commissioning (see operating manual
for the servo amplifier).
2. Wire up the safety card
INFORMATION
Please note the guidelines given under "Wiring".
Connect the 24 VDC supply voltage ("+" to X30/10, "–" to X30/21)
INFORMATION
Do not switch on the supply voltage at this point.
Wire up the inputs and outputs that have been configured. Please
note that the inputs "SS1 Activate" and "SS1 SIL3/Reset" must al-
ways be connected.
3. Connect the configuration PC to the servo amplifier or motion
control system
Connect the PC to the servo amplifier or motion control system
(RS 232 or Ethernet).
Set the interface in the Configurator (see the Configurator's online
help).