5. Set the S1 slide switch to Not Terminated (not labeled on the board) because the ERB will be in
the middle of the daisy chain configuration. The S2 slide switch should already be set to ERB.
Figure 2-183. Setting the switches
6. Reinstall the RFI cover.
a. Slide the two grommets back into the keyhole openings on the top and bottom of the RFI
cover. Hold the RFI cover over the studs against the rear wall. Make sure wires are not
pinched.
Figure 2-184. RFI rubber grommet
b. Attach the cable from the second ERB or FlexLock to the 6 position connector in the ERB.
Secure the cable through the double D holes using the grommets provided.
Figure 2-185. Six position connector
© 2011 Omnicell, Inc.
External Return Bin Installation and Service Guide/67-2038 Rev D
Installation Instructions 2-75
Daisy Chains