Chapter 6 Installation and initial startup
Connection to supply voltage
Requirements
Power supply is installed close to or (max. 1,5 m distant) from the labeling site (s.
Chapter: "Specifications" on page 22).
Main switch is in OFF/ 0-position
Power cabling is available
Instruction
Please connect the labeling system with the power supply as follows.
Step
1
2
3
4
Version: 30.07.14
Procedure
Connect the power voltage cable with the power socket.
Risk of injury from pulling in and crushing!
Immediately after turning on, several system parts make a reference run or
move to its home position!
Maintain a distance from powered system components.
Turn on the main switch.
Turn on the machine and control the running directions of the drives. If the
drives run against the intended driving direction, turn off the system
immediately. The electrical rotating field must be changed in this case by an
Electrician.
Stop the labeling station and turn off the main switch.
Page 31 of 57
40001136 Geset 125
GB